High Court: Dublin Airport Authority’s failure to comply with planning condition was genuine mistake
A group of residents, who sought declarations that work carried out by Dublin Airport Authority in preparation for a new runway was unauthorised development, have lost their application in the High Court.
About this case:
- Judgment:
Sympathising with the applicants’ concerns, Mr Justice Max Barrett accepted that removal of asbestos from the site was carried out a number of weeks before a Waste Management Plan was submitted to the Council; but stated that the breach was a genuine oversight.
St. Margaret’s Concerned Residents Group and 22 individuals applied to the High Court for declaratory reliefs under s.160 of the Planning and Development Act 2000 (PADA).
Two principal reliefs were sought:
Background
In August 2007, An Bord Pleanála granted planning permission for the development of a new runway at Dublin Airport. Due in part to the recession, DAA did nothing to proceed with the development until 2016. The court heard that the applicants objected to the development from the outset.
Described as a substantial infrastructural development involving a 3.1km long and 75m wide runway; the build required the demolition of various structures, the closing of portions of roads, and realignment of roads.
Granting permission, An Bord Pleanála attached various conditions to the permission, particularly Condition 12 that was the focus of the applicants’ case.
Condition 12 of the runway planning permission stated: “Prior to commencement of development, the developer shall submit to the planning authority for written agreement a comprehensive environmental protection plan to minimise the impacts of the construction processes…”
Justice Barrett explained that Condition 12 shows that, from the outset, it was clear that An Bord Pleanála was prescribing the need for DAA, to provide for environmental impact mitigation by way of a comprehensive environmental protection plan.
Oversight
The Waste Management Plan which provided for the disposal of hazardous waste, including asbestos, was lodged with Fingal County Council on 10th February 2017.
Among the documents exhibited by Mr Dee, a town planner with Dublin Airport Authority, was a Waste Disposal/Recovery Certificate. It was stated on this certificate that on 2nd December 2016, Rilta collected 327kg of asbestos that required disposal as a result of “Runway Enabling Works”.
In his affidavit, Mr Dee averred that: “The WMP was not submitted to the planning authority for its approval after the plan had been agreed … on 12 December 2016. This was entirely due to an oversight on my part, which occurred in the context of the overall complexity of this project and the fourteen other conditions requiring matters to be attended to prior to the commencement of development, including the eight other aspects of Condition no. 12.”
The court accepted that the error was entirely innocent “and neither contrived nor malign”, as was the related error that arose due to the “genuine belief that the daa had fully complied with all ‘prior to commencement of development’ conditions.”
Decision
Justice Barret explained that the dispute centred on the commencement of development without the required previous satisfaction of a planning condition that was intended to protect the community and the environment from the effects of that development; and set out the factual and legal considerations he was particularly influenced by:
Exercising the discretion under s.160 and declining to grant any of the reliefs sought, Justice Barret sympathised with the applicants but said “aws matter; rules matter; but mistakes happen”.